Schedule Management

❦

Why Schedules Slip

People consistently underestimate how long tasks take, a tendency called the planning fallacy (Kahneman & Tversky, 1979). In a well-known study of students writing their honours theses, Buehler et al. (1994) found that students' "best guess" completion times were far too optimistic, and that even their "worst case" estimates were often exceeded. The remedy is not to plan more optimistically but to use data, ranges, and buffers.

Steps in Schedule Development

1. Define activities from the work packages in the WBS.

2. Sequence them, identifying dependencies.

3. Estimate durations.

4. Develop the schedule and find the critical path.

5. Control it through regular tracking and updates.

Dependencies

The usual relationships are finish-to-start (B cannot start until A finishes), start-to-start, finish-to-finish, and start-to-finish. A lead lets a task start before its predecessor finishes, and a lag adds a delay. Also distinguish hard (logical, unavoidable) from soft (preferred) dependencies, and external dependencies, such as waiting for ethics approval or equipment delivery.

Estimating Durations

TechniqueIdea
AnalogousUse the actual duration of similar past tasks
ParametricUse a unit rate, such as hours per interview transcript
Bottom-upEstimate small pieces and add them up
Three-point (PERT)Combine optimistic (O), most likely (M), and pessimistic (P) estimates
Expert judgmentAsk people who have done it before

The PERT formula is (O + 4M + P) / 6, and the standard deviation is about (P − O) / 6 (Malcolm et al., 1959). For example, if a task is estimated at 4 days optimistic, 6 most likely, and 14 pessimistic, the expected duration is (4 + 24 + 14) / 6 = 7 days, with a standard deviation of about 1.7 days.

The Critical Path Method

The critical path is the longest sequence of dependent tasks, and it determines the shortest possible project duration (Kelley & Walker, 1959). Tasks on it have zero float (slack); a delay to any of them delays the whole project.

Worked example.

TaskDuration (days)Predecessors
A. Finalize protocol3None
B. Order and set up equipment4A
C. Recruit participants2A
D. Run experiments5B, C
E. Write results2D

There are two paths: A-B-D-E, which is 3 + 4 + 5 + 2 = 14 days, and A-C-D-E, which is 3 + 2 + 5 + 2 = 12 days. The critical path is A-B-D-E (14 days). Task C has 2 days of float, which means it can slip by two days without delaying the project.

Compressing a Schedule

Crashing adds resources to critical tasks, which costs more money.

Fast tracking runs tasks in parallel that were planned in sequence, which adds risk and rework.

Reducing scope is often the most honest option, and the best one for students.

Gantt Charts and Milestones

A Gantt chart shows tasks as bars against a timeline, along with dependencies and milestones. A milestone is a zero-duration marker of an important event, such as "ethics approval received" or "first draft complete."

Buffers and Critical Chain

Goldratt (1997) argued that individual task estimates contain hidden safety, which is wasted through procrastination (the "student syndrome") and multitasking. His critical chain approach removes padding from individual tasks and places a shared project buffer at the end. For a thesis, add a visible buffer of 15 to 25 percent of the remaining time, and protect it.

Schedule in Agile Projects

Agile teams plan in short timeboxes (Sprints or iterations), estimate work in relative units such as story points, and forecast completion from their measured velocity (Cohn, 2005). The plan is updated every cycle based on what was actually delivered.

Typical Academic Timelines

StageBachelor's (about 15 weeks)Master's (about 12 months)Doctoral (about 4 years full-time)
Initiation and proposalWeeks 1 to 2Months 1 to 2Year 1
Planning and ethicsWeeks 2 to 4Months 2 to 3Year 1
Execution (fieldwork, experiments, design)Weeks 4 to 10Months 4 to 8Years 2 to 3
Analysis and writingWeeks 10 to 14Months 8 to 11Years 3 to 4
Closing and submissionWeek 15Month 12Final months

These are illustrations only. Your institution's calendar governs.