Stakeholder and Communication Management

❦

Stakeholders are the individuals and groups who affect or are affected by a project. Poor stakeholder management is a leading cause of project trouble, and the eighth edition of the PMBOK Guide lists Stakeholders as one of its seven performance domains (PMI, 2025).

Identifying and Analyzing Stakeholders

Begin with a brainstorm: sponsors, clients, users, team members, supervisors, funders, regulators, partners, suppliers, the public, and those who may oppose the project. Then analyze them.

Power-interest grid (Mendelow, 1981):

Low interestHigh interest
High powerKeep satisfiedManage closely
Low powerMonitorKeep informed

Mitchell et al. (1997) offer a richer model, classifying stakeholders by their power, legitimacy, and urgency. The more of these attributes a stakeholder has, the higher the priority.

Stakeholders in Academic Projects

StakeholderTypical interestApproach
SupervisorQuality, progress, and your developmentRegular meetings, honest updates
Committee or examinersRigor and contributionEarly feedback, clear milestone reports
Ethics boardParticipant safetyComplete, early applications
Funder or sponsorOutputs and valueReports and milestone delivery
ParticipantsFairness and privacyClear information and consent
Industry partnerPractical resultsJoint planning and clear agreements
Team membersFair workload and creditAgreed roles and communication

The Stakeholder Engagement Plan

For each important stakeholder record: their interests and concerns, their current and desired level of support, the engagement strategy, and who is responsible. Review it regularly, since stakeholders and their positions change.

Responsibility Charts

A RACI matrix assigns each task or deliverable a person who is Responsible (does the work), Accountable (owns the outcome, ideally one person), Consulted (gives input), or Informed (is told the result). It prevents the common problems of gaps and double ownership.

Communication Planning

A communication plan states who needs what information, how often, by what channel, and from whom. Remember that the number of communication channels grows quickly with team size: the formula n(n − 1)/2 gives 10 channels for five people and 45 for ten. This is a strong argument for keeping teams small and for using structure, such as agendas, shared documents, and regular meetings.

CommunicationFrequencyAudiencePurpose
Team stand-up or check-inDaily or weeklyTeamCoordinate work and surface blockers
Supervisor meetingWeekly or fortnightlySupervisorReview progress, decide next steps
Status reportMonthly or per milestoneSponsor, committeeShow progress, risks, and requests
Milestone reviewAt gatesCommittee, fundersDecide whether to proceed

Good Practice in Meetings and Reports

Send an agenda in advance, assign a note-taker, and record decisions and actions with owners and dates. In status reports, lead with the main message, show progress against the plan, flag risks honestly, and state what you need from the reader. Difficult conversations are best handled early and in person or by video, not in long email chains.